1. As work progresses on the crane jib, this photo shows progress halfway day 2 of the jib work. |
11 August - Inclemant weather can be overcome. |
11 November 2007. The crane runner painted and ready to receive the new deck. |
17 June 2007. At the end of day 2 of undercoating. |
2 December 2007. For sale? One used crane engine, exhaust and fuel tank - a few careful owners. |
2 December 2007. The jib is lowered and time to check for any chipped paint! |
2. An unidentified man hard at work with a needle gun. This made light work of the paint stripping, however the latice jib poses many hard to get areas, which slows down progress. |
23 September 2007. A potential final colour scheme for the crane. Mean while the engine has been installed with connections ongoing. |
23 September 2007. After a rare day of good weather the jib gets the first paint with top coat. |
25 November 2007. The first outing for the mechanically overhauled crane. Still a bit of painting to be done though. |
29 July 2007. A final view of the crane data panel prior to needle gunning off. |
29 July 2007. As become synonymous with this project 2 primers were used producing a strang finish. |
29 July 2007. Part of the way through the paint stripping process. |
29 July 2007. The needle gun in action. |
3. An area of jib ready priming. |
30 September 2007. A new match wagon is being formed from a box van. |
30 September 2007. Another good day and a large labour force meant 2 coats of paint on the jib rest. |
30 September 2007. The first top coat on the body. |
4. The biggest element of the work is the replacement of this engine with a new one. |
5 August 2007. Work at the hook end of the jib. |
5 August. A view from the roof giving a good view of the undercoated jib. |
5. Work progresses in the engine compartment in preparation for the new engine. |
6. At the end of day 2 the extent of paint removal and follow on priming on this side can be seen. |
7 October 2007 - Molly rests after a busy session supervising the painting. |
| | | |